The Event Your Risk Register Cannot See: Contracting for the Once-in-a-Decade Shock
Photo: Titanic Belfast, CC BY 2.0, via Wikimedia Commons
Every large organisation has a risk register, and almost every risk register tells the same story. It lists the incidents of the past five years, scores them for likelihood and impact, and allocates owners. The exercise is disciplined, documented and, for the purposes of contracting, largely beside the point. The events that genuinely threaten a business are rarely on the list, because they have not happened yet and nobody has a template for discussing them.
The consequence is visible in the contract stack. Liability caps are calibrated to a distribution of losses the business has already experienced: a multiple of annual fees, a figure within the insurance programme, a number that a procurement committee can approve without escalation. Those caps are sensible for the failures that occur regularly. They are not designed for the shock that occurs once in a decade and takes the balance sheet with it.
The register describes the recent past
The bias is structural rather than careless. Workshops are attended by people whose reference points are recent incidents, and committee dynamics reward precision over speculation. An item that scores low on likelihood and unquantifiable on impact is difficult to defend in a meeting, so it is noted, parked and forgotten. The tail is not ignored because it is unlikely. It is ignored because it is hard to describe.
Yet the events that break contracts have a recognisable shape. A single supplier of a critical service fails. A regulator withdraws a permission. A cyber incident removes access to systems for weeks. A change of law makes performance unlawful. Each is unlikely in any given year; none is implausible over a ten-year term.
A cap built on fees cannot absorb a tail event
Annual fees are a reasonable proxy for the value of a contract and a poor proxy for the harm its failure can cause. A modest software service may cost a hundred thousand pounds a year and support the operation of a distribution network. A cap set at the fees measures the wrong thing.
The answer is not to remove caps; few suppliers will accept that and fewer still will price it. The answer is to differentiate. A base cap for ordinary breach, expressed by reference to fees, preserves the commercial bargain. Above it, specified catastrophe categories can attract a sub-cap or a super-cap, triggered by defined events rather than by the size of the loss alone. Carve-outs for confidentiality, data protection and regulatory breach already follow this pattern; business interruption and continuity failure deserve the same treatment.
Material adverse change: the clause that argues with itself
MAC clauses are notoriously difficult to draft because each party wants them to mean something different. A buyer wants a broad discretion; a seller wants a list of excluded market conditions. The result is often a clause that will be litigated rather than applied.
Where a MAC is the principal protection against a tail event, it should be tied to something observable. Defined thresholds, a specified assessment period, a named independent expert and a decision timetable all reduce the scope for argument. An exclusion for market-wide effects is defensible only if the beneficiary has another route to protection; otherwise the clause has been drafted to look robust and behave as though it were absent.
Continuity obligations that assume the supplier still exists
Business continuity commitments are frequently drafted as a promise to have a plan. The plan is rarely seen, never tested and not updated. When continuity matters, the commitment should be evidential: a plan delivered within a stated period, tested at defined intervals, with the results shared, and with a duty to remedy material gaps within an agreed timetable. The obligation should survive a change of control of the supplier, since a new owner's priorities are not the customer's.
Step-in rights with no means of stepping in
A step-in right is only as good as the machinery behind it. To take over a failing service a customer needs access to systems, credentials, documentation, key personnel and, often, licences held in the supplier's name. If none of that has been arranged in advance, the right cannot be exercised when it is needed.
Practical drafting therefore looks beyond the clause: a step-in deed with named third parties, escrow of credentials and source materials, an obligation to identify key personnel and to notify changes, and a cost-allocation mechanism that makes the arrangement workable rather than theoretical. Step-in also needs a trigger that is objective and quick. A right exercisable only after sixty days of documented failure is a right exercisable after the customer has already lost the season.
Termination as a cliff edge
Termination is the remedy of last resort, and it is frequently worthless in a tail event. Exercising it leaves the customer without the service, without the data and without the capability to substitute another provider. Exit assistance should therefore be drafted as a substantive obligation: a transition period, data return in a specified format, cooperation with a successor, and a price that was agreed when both parties were calm.
A drafting approach: tiers, triggers and time
The method is not complicated. Build three tiers of response: continuity obligations, step-in rights, and exit assistance. Attach each to objective triggers and a decision timetable measured in days rather than quarters. Then test the whole structure against a scenario that is not on the risk register, and see where it fails. Contracts cannot prevent a catastrophe, but a contract drafted for one turns an existential event into a managed one.