Before the Event: Five Points Where Force Majeure Clauses Quietly Fail
Photo: Barry Hughes, CC BY-SA 2.0, via Wikimedia Commons
There is no general doctrine of force majeure in English law. The common law doctrine of frustration exists, but it is narrow: it requires an obligation to have become incapable of performance, or to have been transformed into something radically different from what was agreed. Mere inconvenience, delay or sharply increased cost will not ordinarily suffice. For practical purposes, therefore, relief from performance depends entirely on what the contract says.
That places unusual weight on a clause that is typically negotiated late, drafted quickly and never rehearsed. The failures below are not exotic. They appear in ordinary commercial agreements, and they are usually invisible until the first serious disruption arrives.
First fault: notice provisions drafted as an afterthought
A force majeure clause is frequently accompanied by a notice requirement of seven days, or 'immediately', or 'as soon as reasonably practicable', with the sanction that a party failing to notify loses all relief. Suppliers accept the wording because they expect never to use it.
When an event occurs, the practical obstacles multiply: the person who would give notice is managing the disruption, the recipient has changed, and nobody is certain whether the clause requires notice of the event, notice of its effect, or both. Disputes then turn on whether notification three days after the event was 'immediate'.
A workable provision separates the obligation to notify from the availability of relief. It allows a short window after the party becomes aware, not after the event occurs; it names two or more recipients by role; it specifies what the notice must contain, including the affected obligations and an estimate of duration; and it permits periodic updates rather than treating the first notice as final.
Second fault: a mitigation duty with no standard attached
Most clauses require the affected party to use reasonable endeavours to mitigate. Few say what that obligation actually demands. Does it require a second source of supply, alternative logistics, overtime working, or simply a demonstrable search for alternatives?
Ambiguity here is expensive, because mitigation is assessed after the fact by people who can see what else was possible. The remedy is procedural rather than linguistic: require the affected party to produce a mitigation plan within a stated period, to keep records of the alternatives considered and rejected, and to update the counterparty at defined intervals. A documented effort is far easier to defend than a recollected one.
Third fault: the excluded events list that swallows the clause
The carve-outs are where force majeure clauses are quietly dismantled. Typical exclusions include changes in law, changes in cost or market price, financial hardship or lack of funds, failure of a party's own subcontractors, and weather that is unusual for the parties but normal for the season.
Some exclusions are perfectly reasonable. Others are drafted so broadly that almost every realistic disruptive event is captured by one of them. A change in law exclusion placed alongside a clause that lists compliance with law as the only foreseeable event is a clause that has agreed to do nothing. It is also worth restating the obvious: force majeure ordinarily relieves performance, not payment. A well-drafted clause says so expressly rather than leaving the point to inference.
Fourth fault: the supply chain that sits outside the clause
The most common modern failure is structural. A supplier's ability to perform depends on a chain of third parties, but the clause is written as though performance were a solo act. If it requires the event to be outside the affected party's reasonable control, a subcontractor's failure may fall inside it.
There are two honest options. The first is to extend relief expressly to failures of named or tiered suppliers, subject to conditions such as approved substitution lists, audit rights and a duty to pursue contractual remedies upstream. The second is to refuse the extension and price the risk into the deal. What does not work is a clause that gestures at 'any act of a third party' without deciding which third parties are within the ring.
Fifth fault: no consequence written for the end of the event
Relief from performance is only half the clause. The other half is what happens next: whether obligations are suspended or extinguished; whether time is extended; whether accrued rights survive; whether prepayments are refunded; and what happens to a backlog that accumulated during suspension.
Most importantly, there should be a long stop. Without one, a contract can remain suspended indefinitely, with neither party able to plan and both reluctant to terminate first. A long-stop date, followed by a defined termination right and a mechanism for dealing with work in progress, converts a paralysis into a decision.
An audit for 2026 contracts
Take the clause and read it against six questions: what counts as an event, and who must prove it; what standard of mitigation applies and how it is evidenced; which events are excluded and whether those exclusions leave the clause with any reach; whether the supply chain is inside or outside; how notice works and what happens if it is late; and what exit exists when the disruption does not end. A clause that cannot answer all six is not a risk allocation. It is a paragraph waiting to be argued about.